1. Please provide the number of times your Trust called in emergency contractors or builders for unplanned maintenance and repair works in 2022?
0 – Our internal Estates team provide a first response to all emergency situations in order to make safe. Any long-term resolution/repair required may then be undertaken by contractors, or our internal Estates Team, depending on the works required.
2. Please provide the total cost of emergency contractors or builders for unplanned maintenance and repair works in 2022?
£0 – As per above, all emergency responses are dealt with by our internal Estates Team, where possible.
3. Please provide the largest cost for a single unplanned maintenance and repair work in 2022?
£11,292.00 non-emergency, but unplanned maintenance and repair work..